“For VA’s four largest medical-facility construction projects, when comparing November 2012 construction project data with the cost and schedule estimates first submitted to Congress, cost increases ranged from 59 percent to 144%, representing a total cost increase of nearly $1.5 billion and an average increase of approximately $366 million per project. The schedule delays ranged from 14 to 74 months with an average delay of 35 months per project.”
— From a Government Accountability Office report, here, released Friday into Department of Veterans Affairs' hospitals under construction.